單項(xiàng)選擇題

A switch that is to be added to the production network has been preconfigured (trunks, VLANs, VTP, and STP) and was tested in your lab. After installing the switch into the network, the entire network went down. 
What might explain what happened? ()

A.The new switch happened to be running Cisco Catalyst operating system, while the other network switches were running Cisco IOS Software.
B.The configuration revision of the new switch was higher than the configuration revision of the production VTP domain.
C.The link costs on the new switch are set to a high value, causing all ports on the new switch to go into a forwarding mode and none into blocking mode, thereby causing a spanning-tree loop.
D.The ports connecting to the two switches have been configured incorrectly. One side has the command switchport mode access and the other switchport mode trunk.


您可能感興趣的試卷

你可能感興趣的試題

1.單項(xiàng)選擇題

You have just created a new VLAN on your network for inter-VLAN routing.  
What is one step that you should include in your VLAN-based implementation and verification plan?()

A.Verify that different native VLANs exist between two switches for security purposes.
B.Verify that the switch is configured to allow for trunking on the switch ports.
C.Verify that each switch port has the proper IP address space assigned to it for the new VLAN. 
D.Verify that the VLAN virtual interface has been correctly created and enabled.

2.單項(xiàng)選擇題

You have just created a new VLAN on your network for inter-VLAN routing. 
What is one step that you should include in your VLAN-based implementation and verification plan?()

A.Verify that different native VLANs exist between two switches for security purposes.
B.Verify that the switch is configured to allow for trunking on the switch ports.
C.Verify that each switch port has the proper IP address space assigned to it for the new VLAN. 
D.Verify that the VLAN virtual interface has been correctly created and enabled.

3.單項(xiàng)選擇題

You have just created a new VLAN on your network.
 What is one step that you should include in your VLAN-based implementation and verification plan? ()

A.Verify that trunked links are configured to allow the VLAN traffic.
B.Verify that the switch is configured to allow for trunking on the switch ports.
C.Verify that each switch port has the correct IP address space assigned to it for the new VLAN.
D.Verify that different native VLANs exist between two switches for security purposes.

4.單項(xiàng)選擇題

You have just created a new VLAN on your network.
 What is one step that  you should include in your VLAN based implementation and verification plan? ()

A.Verify that different native VLANs exist between two switches for security purposes.
B.Verify that the VLAN was added on all switches with the use of the show vlan command. 
C.Verify that the switch is configured to allow for trunking on the switch ports.
D.Verify that each switch port has the correct IP address space assigned to it for the new VLAN.

5.單項(xiàng)選擇題What is a critical piece of information that you should have when creating a VLAN-based implementation plan?()

A.approval from senior management
B.end-user requirements
C.IEEE 802.1X authentication parameters
D.a summary implementation plan

最新試題

Which statement is correct about the use of the virtual interface on a WLC ?()

題型:?jiǎn)雾?xiàng)選擇題

Refer to the exhibit. Which statement is true about the output?()

題型:?jiǎn)雾?xiàng)選擇題

If G1/0/1 on DS1 is shutdown, what will be the current priority value of the Vlan105’s group on DS1 ?()

題型:?jiǎn)雾?xiàng)選擇題

Which two statements are true when the extended system ID feature is enabled? ()

題型:多項(xiàng)選擇題

Refer to the exhibit. For what purpose is the command show ip cef used?()

題型:?jiǎn)雾?xiàng)選擇題

Refer to the exhibit. Initially, LinkA is connected and forwarding traffic. A new LinkB is then attached between SwitchA and HubA. Which two statements are true about the possible result of attaching the second link?()

題型:多項(xiàng)選擇題

Refer to the exhibit. What does the command channel-group 1 mode desirable do? () 

題型:?jiǎn)雾?xiàng)選擇題

Based on the show spanning-tree vlan 200 output shown in the exhibit, which two statements about the STP process for VLAN 200 are true? ()

題型:多項(xiàng)選擇題

Refer to the exhibit. All network links are FastEthernet. Although there is complete connectivity throughout the network, Front Line users have been complaining that they experience slower network performance when accessing the server farm than the Reception office experiences. Based on the exhibit, which two statements are true?()

題型:多項(xiàng)選擇題

Refer to the exhibit. LACP has been configured on Switch1 as shown. Which is the correct command set to configure LACP on Switch2?()

題型:?jiǎn)雾?xiàng)選擇題