Project work packages are typically decomposed into smaller components called activities to provide a basis for()scheduling, executing, and monitoring and controllingthe proj ect work.
A.reviewing
B.estimating
C.auditing
D.expecting
您可能感興趣的試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2012年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
你可能感興趣的試題
Define Activities is the process ofidentifying the specific actions to be performed toproduce the()
A.projectelements
B.work drafts
C.workpackage
D.projectdeliverables
During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.
A.proceedings
B.controls
C.forecastings
D.Prelibations
The receiving activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understanding is reached on the meaning of the requirements. The result ofthis analysis and dialog is an()set of requirements.
A.agreed-to
B.agree-to
C.agree-to-do
D.agree-with
()involves using mathematical techniques to forecast future outcomes based onhistorical results.
A.Trendanalysis
B.Qualityaudit
C.Defect repair review
D.Flowcharting
Performing()involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.
A.qualityplanning
B.qualityassurance
C.qualityperformance
D.quality control
最新試題
You are working on the cost budget for one project. Which of the following is true()
空白(4)處填()
空白(3)處填()
空白(3)處填()
空白(1)處填()
空白(1)處填()
In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
空白(2)處填()
空白(1)處填()
Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.