單項選擇題

You are working on the cost budget for one project. Which of the following is true()

A.This process assigns cost estimates to project activities including risks and contingency plans.
B.The cost baseline will be used to measure variances and future project performance.
C.This process assigns cost estimates for expected future period operating costs.
D.The cost baseline is the expected cost for the project.


你可能感興趣的試題

1.單項選擇題An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

A.Total float for the activity is 9 days.
B.The early finish date ofthe activity is the end ofthe day on the 14th.
C.The late finish date is the 25th.
D.The activity can be completed in 2 days ifthe resources devoted to it are doubled.

5.單項選擇題

Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

A.executive IT manager
B.projectmanger
C.change control board
D.projectsponsor