()is a property of object-oriented software by which an abstract operation may be performed in different ways in different classes.
A.Method
B.Polymorphism
C.Inheritance
D.Encapsulation
您可能感興趣的試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2012年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
你可能感興趣的試題
The strategies for handling risk comprise of two main types: negative risks, and positive risks. The goal ofthe plan is to minimize threats and maximize opportunities. When dealing with negative risks, there are three main response strategies(),rransfer ,Mitigate.
A.Challenge
B.Exploit
C.Avoid
D.Enhance
The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.
A.Riskldentification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
D.Risk Monitoring and Control
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.
A.analyze
B.track
C.level
D.extend
Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.
A.milestone
B.baseline
C.quality
D.work
Project work packages are typically decomposed into smaller components called activities to provide a basis for()scheduling, executing, and monitoring and controllingthe proj ect work.
A.reviewing
B.estimating
C.auditing
D.expecting
最新試題
空白(1)處填()
空白(1)處填()
An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.
空白(5)處填()
空白(2)處填()
Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.
In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.
空白(3)處填()
Contract closeout is a process that involves()