單項(xiàng)選擇題

 The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

A.costaggregation
B.reserve analysis
C.parametricestimating
D.funding limit reconciliation


你可能感興趣的試題

1.單項(xiàng)選擇題

Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

A.executive IT manager
B.projectmanger
C.change control board
D.projectsponsor

7.單項(xiàng)選擇題

In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()

A.Strongmatrix
B.Projectized
C.Projectcoordinator
D.Weakmatrix

10.單項(xiàng)選擇題

You are working on the cost budget for one project. Which of the following is true()

A.This process assigns cost estimates to project activities including risks and contingency plans.
B.The cost baseline will be used to measure variances and future project performance.
C.This process assigns cost estimates for expected future period operating costs.
D.The cost baseline is the expected cost for the project.