()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

A.Planned value
B.Earned value
C.Actual cost
D.Cost variance


最新試題

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

題型:單項選擇題

Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

題型:單項選擇題

The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

題型:單項選擇題

()is a category assigned to products or services having the same functional use but different technical characteristics. It is not same as quality.

題型:單項選擇題

The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

題型:單項選擇題

In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.

題型:單項選擇題

On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

題型:單項選擇題

Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

題型:單項選擇題

Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

題型:單項選擇題

()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.