() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
A.projectacceptance
B.scopeverification
C.scopedefinition
D.WBS Creation
您可能感興趣的試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專(zhuān)業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專(zhuān)業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專(zhuān)業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專(zhuān)業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專(zhuān)業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專(zhuān)業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2012年計(jì)算機(jī)技術(shù)與軟件專(zhuān)業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
你可能感興趣的試題
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
A.controls
B.baselines
C.projectstakeholders
D.projectmanagers
() is a measurable, verifiable work product such as specification. feasibility study report, detail document, or working prototype
A.milestone
B.deliverable
C.etc
D.BAC
The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.
A.costaggregation
B.reserve analysis
C.parametricestimating
D.funding limit reconciliation
最新試題
空白(5)處填()
空白(1)處填()
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.
空白(1)處填()
空白(1)處填()
空白(2)處填()
空白(3)處填()
There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.
空白(3)處填()