A customer is installing an HMC-managed Power 720 with two partitions, one for Production the other for Testing. They plan to use the Testing partition only occasionally and want to minimize hardware.
Which of the following meets these requirements?()

A.Create a system profile for each partition. Assign all needed resources as 'required'.
B.Define all system resources as 'desired' on the Testing partition. Activate only as needed.
C.Create two shared processor pools. Assign the minimal I/O resources required for each partition to the shared pools.
D.Create both partitions with minimal 'required' resources, and optional resources as 'desired'. Activate each partition as necessary.


您可能感興趣的試卷

你可能感興趣的試題

1.單項(xiàng)選擇題How can resource allocations for an active partition on a Power 750 be changed immediately and permanently?()

A.Use Capacity on Demand to add the resources.
B.Use DLPAR to add the resources and select the 'permanent' option.
C.Use DLPAR to add the resources, and change the partition profile.
D.Use an Operating System command to permanently request the resources.

2.單項(xiàng)選擇題Which of the following includes Active Memory Sharing (AMS)?()

A.PowerHA Enterprise Edition
B.PowerVM Enterprise Edition
C.VMControl Enterprise Edition
D.Systems Director Enterprise Edition

4.單項(xiàng)選擇題

A retail customer has an 8-core Power 740 server with 2 partitions. Production has 4 dedicated cores and the test partition has 2 dedicated cores. Both partitions run during the day without problems. At night, batch processing is exceeding the run window. 
Which solution addresses this problem without requiring additional hardware?()

A.Adding VMControl will automate processor resource allocation during peak workloads 
B.Enable Dynamic Symmetric Multithreading in the HMC to balance workloads across processors.
C.Add processing resources during the times they are required using Utility Capacity on Demand.
D.Changing the partitions to Uncapped can make use of additional processor cycles during peak workloads. 

5.單項(xiàng)選擇題

A customer has an HMC-managed Power Systems server with 6 partitions. Four production partitions are subject to varying workloads throughout the day, and two are used for development and testing. The production applications have different licensing limitations on the number of physical cores that may be used. The development partitions can use no more than 1 core. The customer would like to dynamically optimize processor utilization within the licensing limits, with minimal operator intervention. 
Which of the following meets the customer requirement?()

A.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partition maximums to one core. Configure each partition to be capped. 
B.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partition maximums to one core. Configure each partition to be uncapped. 
C.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partitions to use no more than one core. Configure the HMC scheduler to dynamically assign processors among the pools over a day. 
D.Create a shared processor pool for each production partition, with the maximum processor limit set to the licensing limit for the application in the pool. Assign the development and testing partitions to a processor pool with a maximum of 1 core. Configure each partition to use uncapped processing. 

最新試題

A customer wants to migrate their existing compute-intensive POWER6 570 to a Power 770. Which of their existing I/O adapters can be migrated to Power 770 enclosures?()

題型:?jiǎn)雾?xiàng)選擇題

Which system provides the highest performance per core, and the least cost for applications licensed per core?()

題型:?jiǎn)雾?xiàng)選擇題

A customer has a 4-core POWER6 570 with 4 partitions and a 2-port 1Gbps Integrated Virtual Ethernet (IVE) Adapter. They are having problems with throughput on the Ethernet adapter and want to improve performance.Which of the following solutions will help the customer with this issue for the least cost and with the least interruption?()

題型:?jiǎn)雾?xiàng)選擇題

How can resource allocations for an active partition on a Power 750 be changed immediately and permanently?()

題型:?jiǎn)雾?xiàng)選擇題

Which of the following configuration is valid for expansion drawers on a Power 750 with 2 processor board sinstalled?()

題型:?jiǎn)雾?xiàng)選擇題

A customer plans to consolidate two 8-core POWER6 systems with a total of 8 PCI-X adapters, 6 PCIe adapters, and a PCI-X I/O drawer into a 16-core Power 750.Which action allows the most efficient use of existing equipment?()

題型:?jiǎn)雾?xiàng)選擇題

Using the following information: Performance data from an existing system that a new system will replace; Performance estimates that anticipate future workloads; Micro-partitioning and logical partitioning implementations.Which of the following allows a technical sales representative to create a system design which can be imported into an HMC?()

題型:?jiǎn)雾?xiàng)選擇題

A customer has an LPAR with 4 dedicated cores on a POWER7 server with SMT4 enabled. How many logical processors are presented to an application running on this LPAR?()

題型:?jiǎn)雾?xiàng)選擇題

A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which  also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed  systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs.How can they manage the new machines for the least cost?()

題型:?jiǎn)雾?xiàng)選擇題

A customer requires two 12X loops on their new POWER7 system. What is the smallest system that will support two loops?()

題型:?jiǎn)雾?xiàng)選擇題