A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached One 4-port 1Gbps IVE adapter PowerVM Standard Edition. They need to add a GX++ adapter and cable it to an I/O drawer.
Which of the following must also be ordered?()
A.A second IVE adapter
B.A second processor card
C.PowerVM Enterprise Edition
D.An additional cable-management arm
您可能感興趣的試卷
你可能感興趣的試題
A customer has a 4-core POWER6 570 with 4 partitions and a 2-port 1Gbps Integrated Virtual Ethernet (IVE) Adapter. They are having problems with throughput on the Ethernet adapter and want to improve performance.
Which of the following solutions will help the customer with this issue for the least cost and with the least interruption?()
A.Order a 2-port 1Gbps Ethernet LAN adapter.
B.Order a 2-port 10Gbps Ethernet LAN adapter.
C.Upgrade the IVE adapter to a 4-port 1Gbps IVE adapter.
D.Upgrade the IVE adapter to a 2-port 10Gbps IVE adapter.
A.1, 2, or 4
B.2, 4, or 6
C.2, 4, or 8
D.4, 6, or 8
A.Power 730
B.PS700 Blades
C.PS702 Blades
D.PS703 Blades
An end user is deploying Blade servers to replace obsolete rack mounted servers. In addition to AIX Web server and database workloads, they also have Windows workloads.
Which Blade is designed for Windows workloads?()
A.HS22
B.JS43
C.QS21
D.PS701
A.A Power 795 with MaxCore mode
B.A Power 780 with MaxCore mode
C.A Power 755 with TurboCore mode
D.A Power 780 with TurboCore mode
最新試題
A customer requires their application to have high availability within a data center, and also the ability to recover at a data center located 600km away in the event of an outage.Which system software solution component supports the customer requirement?()
A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached; One 4-port 1Gbps IVE adapterPowerVM Standard Edition; They need to add a GX++ adapter and cable it to an I/O drawer.Which of the following must also be ordered?()
A customer plans to consolidate two 8-core POWER6 systems with a total of 8 PCI-X adapters, 6 PCIe adapters, and a PCI-X I/O drawer into a 16-core Power 750.Which action allows the most efficient use of existing equipment?()
How can resource allocations for an active partition on a Power 750 be changed immediately and permanently?()
A customer would like to configure an uncapped LPAR so that it can use 2 to 8 cores depending on the workload characteristics. With SMT4 enabled, what is the least amount of processing resources which can be configured for the LPAR?()
A retail customer has an 8-core Power 740 server with 2 partitions. Production has 4 dedicated cores and the test partition has 2 dedicated cores. Both partitions run during the day without problems. At night, batch processing is exceeding the run window.Which solution addresses this problem without requiring additional hardware?()
A customer wants to implement the following Blades in BladeCenter H:Two POWER Blades running IBM i partitions.Two POWER Blades running AIX and LinuxFour x86 Blades running Windows.Which of the following design consideration statements is correct?()
A company plans to deploy a two-enclosure, 23-core Power 780 system with AIX, IBM i and Linux in thefollowing configuration: 3 AIX partitions with dedicated network and disk adapters; 1 native IBM i partition acting as a host1 hosted IBM i partition; 2 hosted Linux partitions.Which configuration will provide boot disk capability to all partitions?()
A customer is deploying a new database on a PS701 Blade in a BladeCenter H, and requires redundant network and SAN adapters. Which configuration supports the customer requirement?()
A Power 720 customer using IVM wants to implement dual VIO servers, but is unable to create the second server. What is the most likely reason for this?()