PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
您可能感興趣的試卷
- 2009年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2009年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2010年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2010年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2011年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2011年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2012年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師上半年上午試卷
你可能感興趣的試題
The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
A.project scope statement
B.project requirement
C.project charter
D.product specification
The()provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.projectcharter
The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing
The()defines the phases that connect the beginning of a project to its end.
A.schedule
B.project life cycle
C.temporary
D.milestone
最新試題
In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.
The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.
Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().
空白(2)處填()
An example of scope verification is ().
空白(3)處填()
An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.
There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.
空白(2)處填()