單項選擇題

PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.

A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish


最新試題

In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.

題型:單項選擇題

The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.

題型:單項選擇題

Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

題型:單項選擇題

空白(2)處填()

題型:單項選擇題

An example of scope verification is ().

題型:單項選擇題

空白(3)處填()

題型:單項選擇題

An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

題型:單項選擇題

Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.

題型:單項選擇題

There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.

題型:單項選擇題

空白(2)處填()

題型:單項選擇題